BRIEF-AltaGas commissions Townsend 2A, provides update on propane export terminal
2017年10月2日 / 中午11点50分 / 19 天内

BRIEF-AltaGas commissions Townsend 2A, provides update on propane export terminal

Oct 2 (Reuters) - AltaGas Ltd

* AltaGas commissions Townsend 2A and provides update on north pine and ridley island propane export terminal

* AltaGas Ltd - ‍$125 million project was completed slightly ahead of schedule and approximately $5 million under budget​

* AltaGas Ltd - construction is tracking on budget and ripet is expected to be in service by Q1 of 2019

* AltaGas Ltd - ‍north pine ngl separation facility is tracking under budget and ahead of its previous schedule of Q1 of 2018​

* AltaGas Ltd - ‍north pine NGL separation facility online date now expected in early December 2017​ Source text for Eikon: Further company coverage:

我们的标准:汤森路透“信任原则”
0 : 0
  • narrow-browser-and-phone
  • medium-browser-and-portrait-tablet
  • landscape-tablet
  • medium-wide-browser
  • wide-browser-and-larger
  • medium-browser-and-landscape-tablet
  • medium-wide-browser-and-larger
  • above-phone
  • portrait-tablet-and-above
  • above-portrait-tablet
  • landscape-tablet-and-above
  • landscape-tablet-and-medium-wide-browser
  • portrait-tablet-and-below
  • landscape-tablet-and-below